Location:
Zachary, LA
Client:
Industry:
Forestry, Pulp & Paper
Category:
Industrial Plants
Project Type:
• Construction of biomass boiler structural steel and rough-set equipment installation
• Installation of boiler piping and associated mechanical systems
• Set steel boiler drum over the boiler structure
• Rough-set and placement of major boiler equipment using dual 300-ton cranes in maximum configuration
• Two crane paths utilized from opposing directions to optimize lift sequencing and site logistics
• One crane equipped with superlift to allow assembly and setting of large modular components
• Average manpower of approximately 60 craft personnel over an 8-month duration