Proven execution of complex heavy haul, critical rigging, and mechanical installation for three HRSG units—recognized by Southern Company as a benchmark for productivity and safety
Heavy Haul & Critical Rigging
Executed 200+ critical picks with zero safety incidents. The heaviest being 201 ton steam drums set atop HRSG units at approximately 100 ft above grade
Heavy haul, rigging, equipment setting, and turbine alignment
HRSG goal post and box erection
Stack erection, including drum skids and pumps
Piping & Mechanical
Installed 6,000+ LF of HRSG piping and supports
Performed alloy and high-chrome welding
Balance-of-plant piping systems and supports
Ductwork & Platforms
Erected inlet, outlet, and SCR/CO burner ductwork
Installed permanent platforms and stair towers supporting ongoing plant operations
Safety & Performance Recognition
Triangle Safety Award Recipient (2014) for Southern Company work
Recognized by Southern Company as:
“One of the most productive mechanical contractors ever measured”
A “textbook example” of high-productivity installation
Zero recordable incidents during critical lift operations