NSC erected more than 20,000 tons of structural steel and platforms for the Melt Shop at ThyssenKrupp in Calvert, Alabama.
Erected 20,000+ tons of structural steel framing and platforms supporting the Melt Shop building and and process equipment
Overhead Crane Infrastructure
NSC performed full detailing and erection of the Melt Shop’s overhead crane system, including crane rail layout, alignment, and setting of the bridge cranes
De-Dusting & Environmental Systems
Installed primary de-dusting hood structures, assembled at grade and erected using tandem pick critical lift methods
Coordinated erection of ET-41 and ET-51 duct support steel systems, including large ground-assembled frames to minimize work at elevation
Ductwork & Equipment Rigging
Installed extensive duct support steel and coordinated duct hoisting following roof steel completion
Utilized pre-assembly and modular erection strategies to improve safety and efficiency